What’s happening
White Cross is a planned offshore test and demonstration windfarm, consisting of 6-8 floating turbines which will be based 52km off the North Devon coast. It aims to bring 100MW of electricity ashore via buried cables that cross under Saunton beach and pass under the dunes before heading inland and linking to a new substation at Yelland.
Key consents from North Devon Council and the Marine Management Organisation (MMO) were granted in May–July 2025 with full approval (with 39 conditions) confirmed in August 2025. Construction is expected sometime between 2028 and 2030 (exact timing tbc). Next, the detailed design, surveys, and monitoring plans must be agreed, and further planning permission will need to be obtained Jan 2026 Update: Planning consent doesn't guarantee that White Cross will be built. To go ahead, the project also needs a Contract for Difference (CfD), a government-backed guaranteed price for the electricity it generates, awarded through national auctions. White Cross was not among the projects awarded a CfD in the most recent round, which was announced in January 2026, so it will need to apply again in a future round. Until a contract is secured, the construction timings remain provisional.
Love Braunton with the campaigning support of Save Our Sands has raised £50,000 to carry out a Judicial Review of the council’s decision on the cable route via Saunton Sands, citing environmental and community impact concerns. The campaign continues to be supported by Braunton Parish Council as well as other local prominent businesses and some community organisations. July 2026 Update: In spring 2026 a judge refused permission for the review, and Love Braunton has said it accepts that decision as final. Save Our Sands has said it will continue to engage in the public consultations on the post-consent conditions.
Our position
While we’re not technical experts, EAND’s commitment to renewable energy and a sustainable future couldn’t be stronger and we want this project to be a case study in how to do it right on a dynamic, sensitive coast.
We recognise, with sadness, the divisions that White Cross has created in our community. People hold many different views, and we respect the commitment across our community to holding the project to account.
White Cross have agreed to regular six-monthly meetings with EAND and the NDWSR who represent a diverse set of organisations. We will work constructively with White Cross, but we will be clear and firm about the conditions, monitoring, and transparency the community needs.
We recognise there will be short‑term upheaval from traffic and noise to economic disruption and stress, but we believe the long‑term gains in local jobs, secure clean energy, and reduced emissions will outweigh these impacts.
We will be part of the broader stakeholder conversation on the community benefit fund’s priorities and spending. EAND are not seeking or expecting any financial benefit.
What we will push for
No permanent hard structures on the beach or dunes.
Cables buried deeply enough that:
they are still covered after extreme storms like 2013/14, and
they remain covered as dunes naturally retreat over time with sea-level rise.
Clear public information on exactly where the cable will land and how deep it will be at each point.
Independent monitoring so we can all see what’s happening to the beach, dunes, and waves.
What’s already required
North Devon Council and MMO conditions require detailed surveys and plans covering everything from seabed conditions and marine wildlife to noise and archaeology, with another full seabed survey carried out within a year of construction to ensure the marine environment is properly monitored and protected.
We will publish updates to the development and our conversations with White Cross on this page. If you’d like to get in touch with us, please use our online contact form here — we read every message, though we will not be able to respond to each one individually.
EAND are committed to long‑term environmental progress and to contributing regionally to climate action, with clear benefits for the community and for nature.
Links
White Cross FAQs: https://whitecrossoffshorewind.com/faqs/
Interactive map of the route: https://flotation.maps.arcgis.com/apps/instant/sidebar/index.html?appid=4c1fff06127640ac9f5f943683cf1e64
Public responses from other organisations:
North Devon UNESCO Biosphere: ‘Position on White Cross Application and Development’
North Devon Council: ‘Devon Energy Prospectus’
Oct 2025